Formosa Point Comfort PE Fire: A Force Majeure Playbook for Buyers

A fire hit a polyethylene unit at Formosa's Point Comfort site on Oct. 28 and force majeure is reported. What to verify, ask and line up this week.

Pedro Zaccaria

Pedro Zaccaria

Chief Technology Officer

ShareLinkedInEmailWhatsApp
Petrochemical plant with chimneys and lit pipe racks at dusk, a backdrop for polyethylene supply and force majeure risk

At about 4 a.m. on Wednesday, Oct. 28, a fire broke out in a polyethylene unit and its product storage silos at the Point Comfort, Texas complex of Formosa Plastics Corporation, U.S.A. (Formosa). Nobody was hurt, and Formosa said its safety mechanisms “functioned as intended and contained the incident,” according to the Victoria Advocate.

On Oct. 31, Polymerupdate reported that Formosa had declared force majeure (FM) on part of its PE range, effective Oct. 29, after an operational incident at one production unit. ChemOrbis carried the same report on Nov. 2. That is one reporting chain, and it names no unit, grades, restart date or tonnage. As of Nov. 2, Formosa’s public alerts page carried no notice; customer letters usually go out directly, so that proves nothing either way.

Same plant, same product line, one day apart: the fire and the declaration look like one event, but no published source links them. Your decisions will not wait for one. Pull orders forward? Buy cover? Quote a second origin?

Start with paper. Your contract runs on what your supplier puts in writing; a trade report starts no clock and fixes no quota. Ask today for the written notice, the grade codes it covers and its effective date (why the letter matters).

One clarification: this is the Texas operation, not Formosa’s Taiwan operations (Mailiao) from our Hormuz crisis coverage. Different plant, different region, different event.

Key Takeaways — November 2, 2026

  • The fire is confirmed; the force majeure is reported. Local press confirms the fire; the FM rests on one trade-press chain, with unit, grades and duration undisclosed (what happened).
  • Get the letter before you act. Under US sales law your written election runs from the seller’s notification. Ask for the notice, the grade list and your estimated quota (your contract).
  • Prices were firming before the fire. November increases were already on the table; the outage moves price only if it runs deep into November (prices).
  • Plan in weeks, budget for longer. Earlier Point Comfort declarations ran for weeks and tended to outlast the restart (history).
  • Line up a trial lot now. The same grade from another plant is the fastest swap. Syntex lists one Formosa grade, E924; whether it is covered is not public (swaps).

What happened at Formosa’s Point Comfort plant?

A fire broke out at about 4 a.m. on Oct. 28 in a polyethylene unit and its product storage silos at Formosa’s Point Comfort complex, the Victoria Advocate reported. Polymerupdate reported on Oct. 31 that Formosa declared force majeure on part of its PE range, effective Oct. 29. The unit, grades, duration and tonnage involved have not been made public.

Disclosure. Syntex America lists one Formosa Plastics Corporation U.S.A. grade from Point Comfort, E924 (HDPE film). Whether the reported force majeure covers E924 has not been made public. If E924 is on your order book, ask your Syntex contact for its current status today.

Table 1 sorts the public record into three bins. Only the first is solid ground for a purchasing decision.

Table 1. What is confirmed, what is reported, what is unknown (as of November 2, 2026)
ItemStatusSourceWhat it means for your order
Fire at about 4 a.m. Oct. 28 in a PE unit and its storage silos; no injuries, no indication of off-site impactConfirmed (Formosa’s statement, as relayed)Victoria Advocate, Oct. 28Real, but says nothing about your grades
Cause, extent of damage, whether the unit’s operations are disruptedNot disclosed (as of the Oct. 28 article)Victoria AdvocateDamage drives duration; no figure is public
Force majeure on part of the PE range, effective Oct. 29, one unit affectedReported (one reporting chain)Polymerupdate, Oct. 31; ChemOrbis, Nov. 2Ask for the written notice and its effective date
Unit, family (LDPE, HDPE, LLDPE) and grade listNot disclosedPolymerupdateAsk for the covered grades by code
Duration, restart date, volume offlineNot disclosedPolymerupdateAsk for an estimate and the next update date
Fire as the cause of the force majeureInference; no source states it—Plausible, not proven; act on the letter
Letter text and allocation termsNot published—Ask for your estimated quota in writing

The only public split by PE family comes from Polymerupdate: about 1.9 Mt/y of polyethylene capacity at Point Comfort, according to capacity estimates it relayed. Formosa has not published its own.

Table 2. Point Comfort polyethylene capacity by type, estimates relayed by Polymerupdate
PE familyEstimated capacityWhat the public record saysSyntex catalog
LDPEabout 625 kt/yUnit commissioned Nov. 2020 (Polymerupdate)LDPE grades; no Formosa grade
HDPEabout 800 kt/yUNIPOL swing plant; bimodal high-molecular-weight film (E924, E927) for T-shirt bags and liners, plus blow molding and pipe (Formosa)HDPE grades; E924 listed
LLDPEabout 465 kt/yHexene copolymers, including the FORMAX series (Formosa)LLDPE grades; no Formosa grade
Totalabout 1,890 kt/yOne unit reported affected; which one is not public—

Is all of Formosa’s polyethylene production offline?

No source says so. Polymerupdate’s report describes one unit and cautions against reading the site’s whole PE capacity as lost. Point Comfort runs 20 production units, per Formosa’s own site; how the other PE lines are running has not been published.

A narrow outage can still bite: Polymerupdate notes that covered grades could tighten more than the wider PE market, because other resins are not always workable substitutes. So your letter’s grade list matters more than the site total, and any trader quoting backup tonnes, our trading desk included, should name the producer and plant behind the offer.

What does a force majeure notice mean for your PE contract?

A force majeure notice excuses your supplier only for the product and the period the impediment actually affects, and only as far as your contract’s clause and governing law allow. Your contract stays alive. Under US sales law the seller must allocate fairly and tell you your quota, and you have up to 30 days to choose in writing.

Does force majeure cancel your contract volume?

No. It suspends or reduces the seller’s duty for the affected product. Under the Uniform Commercial Code, delay or non-delivery “in whole or in part” is not a breach when performance has been made impracticable by a contingency whose non-occurrence was a basic assumption of the contract (UCC § 2-615). Under the UN sales convention (CISG), the exemption “has effect for the period during which the impediment exists” (Art. 79(3)).

Two limits matter. Cost alone rarely qualifies: “if the event only makes performance more difficult or expensive, it will not necessarily excuse performance,” attorney David M. Bond of Kane Russell Coleman Logan wrote after Hurricane Harvey in 2017 (Energy Law Today via Lexology). And in Texas, he noted, an act of God excuses nothing without an applicable force majeure clause. The wording you signed outweighs the headline.

How do suppliers allocate PE under force majeure?

When an outage hits only part of a seller’s capacity, US law makes it share what is left. Section 2-615(b) says the seller “must allocate production and deliveries among his customers,” may count regular non-contract customers and its own downstream needs, and may allocate “in any manner which is fair and reasonable.” Then it owes you a number:

“The seller must notify the buyer seasonably that there will be delay or non-delivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.”

— Uniform Commercial Code § 2-615(c), Cornell Law School Legal Information Institute

Formulas vary; we found no trade-press report quantifying PE contract allocations in past Gulf outages. One documented letter shows the mechanics: in 2017, LyondellBasell allocated 1,4-butanediol (a chemical, not PE) from Channelview, Texas, on “purchases made in the prior six (6) months,” with no borrowing ahead and no carry-forward (Everchem, reproducing the letter). Formosa’s own July 2017 letter kept force majeure “and sales control” after its PE units restarted (Platts via Plastemart; dates in the history table).

Your recent purchase history is probably your allocation base, so have it ready; spot buyers sit further back. After Winter Storm Uri, LyondellBasell’s then-CEO said the company did not “have enough volume to even meet the needs of the domestic customers” (Bloomberg via Rigzone), which suggests (our inference) that export and spot volume went first.

Which law governs force majeure when you import PE from the US?

Whatever your contract names, first. If it names nothing and you buy from a US seller in Brazil, Mexico, Chile, Colombia, Peru or Argentina, the default is usually the CISG, whose text has no allocation duty and no 30-day lapse. Three checks:

  1. Read the governing-law and FM clauses. Parties may exclude or vary the CISG (Art. 6). An ICC Force Majeure Clause applies only if incorporated; the 2020 version lets either party terminate once the impediment passes 120 days, unless agreed otherwise (Erdem & Erdem).
  2. If a US state’s UCC governs (a domestic sale, or the CISG excluded in favor of US law): once the seller notifies a material or indefinite delay or an allocation, you may, in writing, terminate the unexecuted portion or take your quota instead (UCC § 2-616). If you do not modify the contract “within a reasonable time not exceeding thirty days,” it “lapses with respect to any deliveries affected.” That clock starts on receipt of the seller’s notification. Excused non-delivery is not a breach, so replacement tonnes are probably on your account rather than claimable as “cover” (§ 2-712); counsel should confirm.
  3. If the CISG applies: all six countries above and the US are contracting states (UNCITRAL), so it governs by default under Art. 1(1)(a), the US reservation notwithstanding. Article 79 shields the seller from damages while the impediment lasts, provided it gives notice of “the impediment and its effect on his ability to perform.” Your other remedies survive (Art. 79(5)). Chile and Argentina made written-form declarations, so put every election in writing.

General information, not legal advice. Have counsel read your clause.

What should you ask your supplier in writing this week?

Seven questions in one email turn a headline into terms you can plan on. A good notice is “factual and specific,” in Bond’s words, so vague answers tell you something too. File the replies, then work through the 10-day checklist.

Table 3. Seven questions to send your PE supplier after a force majeure notice
QuestionWhy askGood answerRed flag
1. Can you send the written notice and its effective date?Contract clocks run on the seller’s notificationA dated letter naming the impediment“It’s in the trade press”
2. Which grade codes and which plant are covered?FM excuses only affected productA list by grade code and unit“Part of the range,” no list
3. What is my estimated quota, and on what base?§ 2-615(c) asks for itTonnes or percent per month, base period stated“We’ll let you know”
4. What is the estimated duration, and when is the next update?Your cover and trial decisions hang on itAn estimate and a dated update cadenceNo update date
5. Does allocation treat contract, spot and export buyers alike?Sellers may include non-contract customers and their own needs (§ 2-615(b))One written rule for all buyersDifferent answers to different buyers
6. What price applies to allocated and extra tonnes?A letter silent on price leaves the invoice openContract price on the quota; extras quoted separatelySurcharges on allocated tonnes
7. Which clause and governing law are you relying on?Decides between a UCC election (up to 30 days) and the CISGA clause number and a named law“Act of God” with no clause cited

While you wait, check your backup-grade list. If a letter leaves your supply unclear, talk to us before you reply.

Buyer reviewing printed contract pages with a pen at a desk, checking force majeure notice terms for polyethylene supply
A buyer reading a printed contract with a pen in hand. The force majeure clause is where the notice, the dates and the remedy are actually decided. Photo: Pexels

Will US polyethylene prices rise in November 2026?

Possibly, though the reported Formosa force majeure is not yet the reason. Dow has 5 ¢/lb on the table for November, S&P Global reports several producers asking 5 to 7 ¢/lb, and buyers are split on whether any of it sticks. We found no published price reaction to the declaration as of November 2, 2026.

Our China inventory buying guide recaps the run-up to Oct. 26; here is what moved since.

What price increases have US PE producers nominated for November?

Two sources, two numbers. S&P Global Commodity Insights, as relayed by Polymerupdate on Oct. 31, reports several US producers proposing 5 to 7 ¢/lb for November. Dow put its own asks on record on its Oct. 22 earnings call, a week before the fire:

“If we’re able to achieve the 7 cents we have on the table for October and the 5 cents in November, that will provide an upside to our Q4 guide. And that’s going to also depend on how far feedstock costs rise.”

— Karen S. Carter, CEO, Dow, ICIS, Oct. 22, 2026

Dow’s November ask sits at the bottom of the S&P range. October is still open: buyers told Argus they saw little to support more increases after September, and on Oct. 30 LyondellBasell said producers “have implemented increases in the market” without a figure (Plastics Today). If an October increase shows up on your invoice, ask which settlement it refers to.

Does the Formosa outage make the increase stick?

Only if it lasts. Polymerupdate reads the outage as support for US prices if it runs into November; a unit back within days changes little. Beyond that, the signals point both ways.

Table 4. US PE price signals heading into November 2026 (as of November 2, 2026)
SignalLatest readingSourceRead-through for your buy
September contract+5 ¢/lb for most contracts, some invoiced at 3 ¢; the first increase since AprilArgus; Plastics NewsYour baseline. Check whether you paid 3 or 5.
October7 ¢/lb nominated; no published October settlement foundICIS; ArgusNo October line without a named settlement.
NovemberDow 5 ¢/lb; several producers 5-7 ¢/lb; participants “remain cautious”ICIS; S&P Global via Polymerupdate; S&P Global, Oct. 30Quote your own customers a range, not a point.
US PE inventoriesDown over 400 million lb in September, five fewer days of cover (ACC data cited by Dow), after four monthly builds through July; LYB says customers run “very, very lean inventories”ICIS; Plastics Today; Plastics Today, Oct. 30Less cushion than in summer to absorb a one-unit outage.
US Gulf ethylene27.00-27.50 ¢/lb on Oct. 28, from 23.50-24.00 ¢/lb on Oct. 12 (Polymerupdate assessment)Polymerupdate; PolymerupdateA firmer cost case for November than three weeks ago.
Pre-fire outlookFlat-to-down for November; “plenty of resin supply and supplier competition”Plastics Technology, Oct. 21The buyer’s case, written before the fire.

Demand is the weak leg: participants cite patchy demand across regions and the usual year-end lull (Polymerupdate). And an ask is only an ask. In June, producers “led by Formosa” pursued a 10 ¢/lb increase; June contracts settled 15 ¢/lb lower (Argus).

Duration is the variable nobody has published. Table 5 maps it to decisions; the history below points to the middle row.

Table 5. How the outage could play out for buyers: a decision framework, not a forecast
If the unit is down for…What you would likely seePrice pressure from this eventWhat to do
DaysDeclaration lifted with a lag; November settles on feedstock, exports and demandLittle to noneBuy as planned. Pay no force majeure premium on spot.
Weeks (restart mid to late November)Allocation on the affected grades; thinner offers on that familySupports the November ask at the marginGet allocation in writing; quote a second origin (origins).
More than a monthThe affected family stays tight into year-end and 2027 contract talksStrongest for that family onlyRun a trial lot now (swap routes); extend cover on exposed grades only.

How do Asian turnarounds change the export picture?

Only at the margin. Polymerupdate lists planned maintenance at a 370 kt/y Honam Petrochemical HDPE/LLDPE swing plant, shut Oct. 15 for about 15 days (that window has closed), and technical idling of at least a third of a 335 kt/y Hanwha Chemical LLDPE plant from Oct. 18. US export prices matter more to your quote.

In early September, US export prices rose 4 to 8 ¢/lb fas Houston, led by high molecular weight HDPE film (Argus). Going into October, momentum had “already softened,” David Barry told Plastics Technology, while Polymerupdate credits Asian and African buying with holding US prices up through October. Our read: mixed, firming into month-end, with Asian naphtha up 19% in October to $1,081/t (ChemOrbis). Every Gulf cargo Asia bids on is one your RFQ competes with.

Which PE swaps can you make quickly, and which need a trial?

The quick swap is the same grade code from stock already in the channel: it needs only a check of the lot certificate. Another producer’s grade in the same family needs at least a line trial, and a change of family means full requalification. We found no published benchmark for how long qualification takes; your spec sets the clock.

Table 6. Three swap routes after a single-plant outage (Syntex working view; relative times, not a published benchmark)
RouteTime to a first lotMain riskWhat must still be testedCatalog example
1. Same grade code, another sourceFastest; limited by where the stock sitsFinite volume, and every affected buyer calls the same holdersLot certificate of analysis against your incoming specE924 shipped before the effective date, if any, sitting in a warehouse or on the water
2. Same family, different producerSlower: sample, lab check and a line trial come firstMatching density and melt flow can hide different comonomers and additivesMelt flow at the same test condition, density, then your line: output, gauge, impact, tear, sealHDPE film: E924 at 0.04 g/10 min (190 °C/2.16 kg) and 0.949 g/cm³, against HF49007 (Chevron Phillips Chemical) at 0.06 and 0.950, and H5604F (SCGC™) at 0.04 and 0.954. LLDPE film: Dow 2645G (0.9; 0.919). LDPE film: Petkim G03-5 (0.30; 0.920). All trial candidates, none an equivalent
3. Different family (say, rebalancing an LLDPE/LDPE blend)Slowest: reformulation, then full requalificationThe film changes. Dow and Sinopec authors in Plastics Technology describe LDPE as the melt-strength and bubble-stability share of a blend, bought at some cost in film strengthFull qualification, plus customer and regulatory sign-offIf the unit is LDPE, our 2027 outlook found that family has the fewest alternatives: qualify the LDPE alternative first

Can you take the same grade from another plant?

Only if another plant or line makes the same code, so ask your supplier first. Otherwise look for stock already landed, cargo afloat or distributor inventory, each lot checked against your incoming spec.

Which HDPE film grades are closest to Formosa’s E924?

By datasheet, Chevron Phillips Chemical’s HF49007 and SCGC’s H5604F, the two HDPE film grades in our catalog with melt flow quoted at E924’s 190 °C/2.16 kg condition. Formosa describes E924 as a high-molecular-weight bimodal resin for T-shirt bags and trash can liners. The trial decides the rest.

  • HF49007 comes from a different company and plant, which hedges a single-unit outage at Point Comfort. It is still Texas supply, so it hedges nothing against a hurricane, port closure or rail problem across the Gulf Coast.
  • H5604F is made primarily at SCG’s Long Son complex in Vietnam, with an alternate source in Thailand. SCG said in April it would suspend Long Son from mid-May; we found no restart report. Until SCGC confirms which plant would make your lot, treat H5604F as a datasheet match, not a source.

Earlier Point Comfort force majeures have named Formosa’s high-molecular-weight film grades (history table); that is scope history, not evidence about this declaration.

In a May story on the Iran war’s hit to packaging converters, a consultant put it plainly:

“[Y]ou can’t just swap those materials out. It takes a long time.”

— Jonathan Quinn, CEO, EGC Consulting, Packaging Dive, May 14, 2026

What must a replacement lot prove before it runs on your line?

That it makes your product to spec, with paperwork to match: a lot certificate, a lab check at the incumbent’s test conditions, a production-scale trial and your customers’ sign-off. For food-contact film, FDA’s 21 CFR 177.1520 sets polymer limits, such as a maximum n-hexane extractable fraction, but no requalification period; you still need the producer’s compliance statement for the grade and your brand owner’s approval.

Our PE supplier scorecard has the full backup-qualification method, with the five-step trial and grade-level substitution rules; our resin selection guide explains why a datasheet alone cannot approve a substitute. The trial is the one step you can start before anyone knows how long the outage lasts.

Warehouse with large clear plastic film rolls on pallets and forklifts, polyethylene film stock for grade substitution
Rolls of clear plastic film stacked on pallets in a warehouse. Film grades are the first place a forced grade substitution shows up on the converter's line. Photo: Pexels

How long do US polyethylene force majeures usually last?

Weeks, in the cases with dated sources. Formosa’s June 2017 force majeure (FM) after a power outage at Point Comfort, Texas ran about five weeks, and its Hurricane Harvey declaration was due to lift about a month after it began. Fire-related and Gulf-wide events ran longer. Plan on weeks and budget for months.

Table 7 lists the US Gulf PE FM episodes we could date, mostly at Point Comfort; the two storm rows each name their measure.

Table 7. US Gulf PE force majeures: what history says about duration (calc. = our arithmetic from dated sources)
EventDeclaredWhat went downRestart or liftMeasure and price effectSource
Formosa Point Comfort power outageJune 27, 2017, on all PE and PP (outage began June 24)Two olefins units, PE, PP and chlor-alkaliAll PE and PP units running by July 17; FM and sales control “through the end of July”; last HDPE line back about July 22. About 5 weeks (calc.)PE and PP “talked tighter in July,” partly on the outage; no ¢/lb figure foundPlatts via Plastemart (June) and Plastemart (July)
Hurricane Harvey (Formosa)Aug. 28, 2017, on PE and PP (complex shut Aug. 24)The whole complexCracker restarted Sept. 5; PE and PP FM lift planned for end-September. About 1 month (calc., planned lift)Market-wide measure, share of US ethylene capacity closed: 61%. North American PE up 4 ¢/lb on average in September 2017, as reportedChemOrbis; Bloomberg (PetroChem Wire data); Plastics News
Formosa olefins unit fireAbout Feb. 7, 2018, on “all of its LLDPE and Formolene bimodal HMW PE” (fire in December 2017)Olefins 1 unitRestart projected for the second half of February 2018, 7 to 10 weeks after the fire (calc.); lift date not foundProducers sought +4 ¢/lb for February and +3 ¢/lb for March: asks, not outcomesICIS; Plastics News; Polyestertime
Winter Storm UriFeb. 16, 2021: Formosa said all its PE, PP and olefins plants were shutGulf-wide freezePer-producer lift dates not found; about 60% of US olefins capacity back by mid-March 2021Measure, share of capacity offline at peak: more than 80% of US olefins and polyolefins. HDPE hit its highest price since 2008 (an index level, not a change)Wood Mackenzie; Plastics Technology; Bloomberg via Rigzone
Formosa HMW film and pressure-pipe PEFeb. 22, 2023HDPE film and pipe grades onlyLift date not foundNot foundPlastics News
This eventEffective Oct. 29 (reported)One unit, not namedOpen: not public as of November 2, 2026No published price reaction found as of November 2, 2026What happened

Fires at this site have run longer than outages. A February 2021 dryer fire put Formosa’s specialty PVC (not PE) under force majeure until July 6, 2021, about four and a half months (calc., S&P Global). Point Comfort also shut during a freeze earlier this year (Plastics Technology).

Treat Uri, a Gulf-wide freeze, as the upper bound for a one-unit outage. A month after the storm, LyondellBasell’s then-CEO was already looking past the restarts:

“I think we’ll be well into the fourth quarter before we see conditions back to normal.”

— Bob Patel, then CEO, LyondellBasell, on polyethylene after Winter Storm Uri, Bloomberg via Rigzone, March 18, 2021

Why does a force majeure outlast the restart?

Because a running unit still has a backlog to clear. In the two dated PE cases, Formosa kept its declaration about 9 to 14 days past the restart in the 2017 power outage, and three to four weeks past the Harvey cracker restart against a planned lift date (our arithmetic from the sources above).

Two more patterns, both our analysis:

  • Scope is narrow at this site. The 2018 and 2023 declarations named specific families and grades, and this year’s is reported as partial too. We could not find whether other grades kept shipping in those episodes.
  • Lifts go unreported. We found no published lift date for three of the five past episodes, and only a planned one for Harvey. Ask your supplier for the lift date in writing instead of waiting for the press.

Assume weeks for this event. The next question is where the tonnes come from in the meantime.

Where can you source replacement polyethylene if US Gulf supply tightens?

Start with other US producers and stock already in your country, then price Asia and the Middle East as slower, costlier backstops. Within about 30 days, the realistic replacement after a one-unit US outage is resin that already exists: another Gulf producer’s lot, a cargo on the water, or material inside your customs territory.

Full origin maps live in our 2027 PE sourcing map and H2 2026 delivery map; Table 8 is the 30-day view after one plant goes quiet. The wider market looks adequately supplied: ICIS expects Latin American PE to stay well supplied through the fourth quarter (our China guide), and West Coast South America HDPE rolled over on Nov. 2 with LLDPE film quoted flat (Polymerupdate).

Table 8. Replacement PE origins for Americas buyers: the 30-day view (as of November 2, 2026)
OriginAvailability readLead time to the AmericasDuty or routing watch-outWhere the full map is
Other US producersWe found no other North American PE force majeure reported for October or November. LyondellBasell finished its Clinton, Iowa turnaround and guides its North American olefins and polyolefins operating rate to 85% for Q4 (Plastics Today). New Orange, Texas HDPE capacity is reportedly coming on stream; start-up unconfirmed (Plastics Today)The shortest deep-sea leg into Mexico and BrazilSame Gulf exposure to storms, ports and rail. Pacific South America: check Panama routingUS Gulf backfill
CanadaWe found no November availability data; ask for a quote and a loading dateDepends on the loading point; askCanadian PE carries its own Brazilian anti-dumping duty (tariff guide)2027 map
Middle EastHormuz was still restricted on Nov. 2: Iran offered to reopen “within two days if Washington meets its conditions,” and two tankers hit mines on an “unauthorized route” (Hellenic Shipping News). ITP reads a July-to-September rebound in Saudi PE shipments to China as rerouting around the straitRoute-dependent; the carrier decides routing and war-risk termsLyondellBasell sees high feedstock and freight costs keeping other regions from meeting export demand (Plastics Today); background in our Hormuz coverageH2 2026 map
Asia, including China re-exportChina PE futures were up 16% to 18% month on month in two Nov. 2 readings (Trading Economics), and Dow says China “is coming back into the market” (ICIS). In Korea, ChemNet reported that Hanwha TotalEnergies permanently halted a 125 kt/y LLDPE line at DaesanThe longest leg; inside 30 days, only on-water cargo countsFor SCGC grades, confirm whether the lot ships from Long Son, Vietnam, or Thailand (see swap routes). Re-export paperwork: China re-export checkChinese HDPE; Korea backup
Already in your customs territoryDomestic and bonded stock. Our Oct. 16 Brazil guide found no Braskem force majeure notice in 2026, and we found nothing newer (Braskem risk)Measured in truck hoursHighest cost per tonne, lowest delivery risk. In Brazil, price imported stock with the 20% import duty includedNearshore inventory

Can Brazilian buyers simply switch to another US producer?

Yes, and the duty line does not move. Brazil’s anti-dumping duty of $199.04/t applies to US-origin polyethylene, on top of the 20% import duty, whichever US plant made it (tariff guide). Swapping origin is where the duty math changes.

Whatever the origin, ask for the loading date and the vessel before you compare prices; our RFQ delivery sheet lists what to request.

What should you do in the first 10 days of a PE force majeure?

Verify the notice before you act on the headline: get the letter, the product list and the effective date from your own supplier. Then map which of your SKUs it touches, check your contract’s clock, count your cover, quote two other origins and book a trial lot. The 10 days are our working window, not an industry rule.

Save the list. The first three steps cost a few emails; the later ones close options if you wait for a restart date.

  1. Verify the notice (day 0). Ask your supplier for the written force majeure (FM) letter, the grades it covers and the effective date; a trade report cannot stand in for it (why). Buying through a trader? Ask whether your lots are covered.
  2. Map your exposed SKUs (day 1). List every grade you take from the affected producer, by plant, with open orders and due dates. Past Point Comfort declarations sometimes covered named families only (history).
  3. Send your questions in writing (days 1–2). Use the seven questions in Table 3 and keep every reply.
  4. Check the law and the clause (days 1–3). Find the governing law and the FM clause, and check whether the CISG is excluded or an ICC clause incorporated. If the UCC governs, diarize your election deadline: a reasonable time, never more than 30 days, from the seller’s notification.
  5. Count your cover (days 2–3). Add stock on hand, cargo in transit and your expected quota, and set it against the production plan. The chain went into this with less cushion than in summer (Table 4); if the gap is real, buffer stock near your plant buys time.
  6. Quote two alternative origins (days 2–5). Send one RFQ to two sources that do not share the affected plant, using our RFQ delivery sheet and the 30-day origin view. A multi-origin trading desk can answer both in one round.
  7. Book a trial lot (days 3–7). Order the closest candidate from Table 6 now. If the FM lifts before the trial ends, you keep a qualified second source for the next one.
  8. Reprice and check your own clause (days 4–7). Read the FM and price-review terms in your own customer contracts. Whether an upstream FM excuses you downstream depends on wording; courts are “not uniform,” Bond wrote in Energy Law Today. Tell customers early and stick to facts.
  9. Document for claims (from day 0). File the letter, each allocation update, your emails, every cover purchase and its price gap to the contract. Records made at the time beat reconstructions.
  10. Decide your fill strategy (days 5–8). Take the quota, top it up from the alternative origins, or end the affected deliveries where your law allows. Book the last leg with transportation that fits the new arrival dates.
  11. Set a restart watch (days 8–10, then weekly). A restart does not put resin on your dock: after Harvey, PetroChem Wire’s Kathy Hall told CNBC that plants were coming back while nothing was moving out of the area. Check Formosa’s alerts page and the trade press weekly, and re-read your letter when a lifting notice arrives.

How Syntex keeps your line running when a supplier declares force majeure

Syntex America helps you cover a force majeure gap without betting on a single plant. Our trading desk quotes polyethylene from several origins, our logistics teams move and hold stock near your line, and the Resin Supply Credit Program funds the replacement tonnes: we supply, you produce and sell, you pay after your operational cycle.

Each costly step in that checklist has an owner on our side:

  • Find the tonnes. Trading quotes PE from several origins and names the producer on every offer, so you know the replacement is not from the same unit.
  • Ship them at a visible cost. Freight forwarding books the cargo and puts freight on its own quote line.
  • Clear them on the right origin. Customs clearance checks classification and origin papers before a supplier change alters your duty, including Brazil’s anti-dumping duty on US PE.
  • Hold the bridge stock. Integrated logistics centers keep cover near your plant until allocation and replacement cargo catch up.
  • Deliver to your schedule. Transportation runs the last leg to your gate on your line’s dates.

Holding an E924 order? Ask your Syntex contact for its status and a trial quote on HF49007, or on H5604F once SCGC confirms which plant would make your lot. Both are trial candidates, not drop-in equivalents.

Short-notice replacement resin can cost more than the contract tonnes it replaces, and the bill lands before your customers pay you. The Resin Supply Credit Program moves that bill to the end of your cycle in three steps:

  1. We supply. Syntex delivers the replacement grade you approved, from the origin you approved.
  2. You produce and sell. The resin runs on your line and your goods ship on your normal schedule.
  3. You pay after your operational cycle. The invoice falls due once your cycle closes, so your customers’ payments can cover it.

Credit lines run from USD 50K to 500K+ for qualified manufacturers; each starts with a credit analysis of your operation, and approval depends on it.

For a useful answer in one round, send us four things:

  • The force majeure letter, or a note that none arrived.
  • The affected grades, monthly tonnage and the share your plant cannot run without.
  • Your cover in days: stock, cargo in transit and any quota offered.
  • Your delivery point and operational cycle, from resin receipt to customer payment.

Bring that to a credit application, or talk to our trading team first about a second-origin quote.

The declaration sets your supplier’s limits. What you do in the next 10 days sets yours.

Frequently Asked Questions

It typically excuses the seller's delivery of the affected product while the impediment lasts; it does not erase your contract. Your clause and governing law set the details. Under UCC 2-615, a US seller with partly affected capacity must allocate fairly and tell you your estimated quota. Ask for both in writing, and have counsel read your clause.

Not as far as any source says, as of November 2, 2026. The Victoria Advocate reported an Oct. 28 fire in a polyethylene unit and its product storage silos. Polymerupdate, which reported the force majeure, put site capacity at about 1.9 Mt/y and said that total is not all offline. The unit, duration and restart date are not public.

Nobody can say yet, as of November 2, 2026. Before the fire, Dow had 5 ¢/lb on the table for November, according to ICIS, and S&P Global reported several producers proposing 5 to 7 ¢/lb, as relayed by Polymerupdate. Polymerupdate said the outage could firm prices if it runs into November. We found no published price reaction.

Weeks to months, depending on the event. Formosa's June 2017 power-outage force majeure at Point Comfort ran about five weeks, its Harvey declaration about a month to a planned lift, and a fire-related PVC force majeure at the site took about four and a half months to lift. In two dated PE cases, the declaration outlasted the restart.

That has not been made public as of November 2, 2026. E924 is the one Formosa Point Comfort grade Syntex America lists, and no public source names the grades the reported force majeure covers. Ask your Syntex contact for its current status. HF49007 and H5604F are trial candidates by datasheet, not equivalents; H5604F's producing plant needs confirming first.

Possibly; your clause and governing law decide. Under US UCC Article 2, a buyer notified of a material delay or an allocation may, in writing, terminate the affected deliveries or take the offered quota. The CISG, which applies by default to US sales into Brazil, Mexico, Chile, Colombia, Peru or Argentina unless excluded, works differently. General information, not legal advice.

Pedro Zaccaria

Written by

Pedro Zaccaria

Chief Technology Officer

Pedro Zaccaria is Chief Technology Officer at Syntex America, where he sets how technology shapes the business, from trading and credit risk to logistics, and leads the use of AI and data in commercial, credit and logistics decisions. He writes on global polymer trade flows, supply chain disruptions, and commodity pricing trends.

Areas of Expertise

Global resin marketsPolyethylene trade flowsSupply chain logisticsCredit risk managementArtificial intelligence

Published on November 2, 2026